19. The public body may not withhold an amount from payment owing to a general contractor for the sole purpose of protecting the claim of subcontractors that have disclosed their subcontract to the public body. Accordingly, the public body cannot require a discharge from the general contractor.
M.O. 2018-01, s. 19.
In force: 2018-08-02
19. The public body may not withhold an amount from payment owing to a general contractor for the sole purpose of protecting the claim of subcontractors that have disclosed their subcontract to the public body. Accordingly, the public body cannot require a discharge from the general contractor.